Earlier explorations, kept as they were
These rooms are how the lab first worked the SolarForm and its robots. Nothing in them is developed further; they stay so the reasoning can be read. Why this one was set aside. Four ways to stand a tree with quadrupeds and temporary props. Each has a fault, stated beside it. The lab now stands a tree one way, on the geared jig with a drone's line on its top, played on the CAD (the Install room).
Earlier studies
Kept as a study, with its fault: the folded leaves reach to 0.6 m under the head, where the legs stand closer than the leaves are wide. Carried on edge, as drawn now, they pass between the legs for all but the last 8 % of the hoist (flat, they crossed a leg for half of it); a head 10.5 m up, not 9.5, would clear them by 12 cm, and its longer legs would buckle sooner.
Stage 1 · 693 trees, 37 Max · 1.3 mo
Stage 2 · 335 trees, 110 Max · 2.2 mo
Stage 3 · 554 trees, 74 Max · 1.7 mo
Side by side
| Tilt-up jig | |||||
|---|---|---|---|---|---|
| Order | whole tree | foundation first | foundation first | whole tree | whole tree |
| Robots at the stake | 3 | 3 | 2 | 3 | 2 |
| Heaviest piece carried | the drive stool, 22 kg | the template, 24 kg | the slew drive, 30 kg | the ring, 22 kg | the jig, on its skids, 70 kg, towed |
| Torque goes | the stool's geared collar → its three pinned feet | the template's head → three pins; the tree itself is never turned | the template's head → three pins; the slew drive's torque arm → the flange | the collar's gear → the hoop → its two pinned feet | the harness's ring gear → the A-frame and sled → the skids → four pins |
| Plumb by | gravity: it hangs from its hub, 140 cm above its centre of mass | three robots walk their guys in or out to a clip-on inclinometer | the drive trims it in its plane; the template set the flange level in the other | the frame: held at the ring's cup and the crown's collar, 2.4 m apart | the harness's collar, set square on the frame |
| Holds plumb to | 7.6 m/s | 6.9 m/s | 9.0 m/s | 9.0 m/s | 9.0 m/s |
| Checks short | stop-work wind, held within 1° by the hook and two robots | stop-work wind, held by one robot's guy | none of 11 | none of 10 | towing the jig on its skids, one robot |
| Product change | none | a hinged flange between the screw and the stem | a hinged flange between the screw and the stem | none | none |
| Left in the ground | the screw and 3 anchors; the stool's and tripod's pins come out | the screw and 3 anchors; the template's pins and the winch's pin come out | the screw and 3 anchors; the template's pins come out and the drive is carried on | the screw and 3 anchors; the ring's, the feet's and the stays' pins come out | the screw and 3 anchors; the jig is towed on |
Stop-work wind 9 m/s; the Waimānalo square's mean wind 6m/s. Every anchor proves itself as it goes in: at its final torque, AC358's correlation gives 7.4 kN allowable each, the screw 27 kN, a temporary pin 4.9kN. Numbers are graded in the ledger; most of the kit's are Form's estimates, to be replaced by a prototype's measurements.
The ground
SSURGO maps the Waimānalo square as silty clay loams and clays, 37–70 % clay, where a 76 mm screw and 25 mm anchors drive well. One unit, Ewa silty clay loam (moderately shallow), sits on coral at 74 cm: a 140 cm screw meets refusal there. Before a row is laid out, a robot drives a probe pin at each stake and logs its torque; where it refuses, the stake moves or the screw is swapped for a shorter one with a fourth anchor.
The brief
- What a professional would do that wasn't asked
- A temporary-works engineer (who props tilt-up panels, rigs towers and sets poles) designs for the worst temporary state, not the finished one: the tree standing but not yet anchored, in wind. They write the erection as stages and check each one; follow every force and torque to the ground, never through a robot's arm; set a stop-work wind; make each anchor prove its own capacity as it is driven; plan the strike as carefully as the set-up, so nothing temporary is left; and question the product: put the foundation in first, which needs a hinged flange between the screw and the stem.
- The rawest material
- Not the room's summary sizes but the soil's horizons from SSURGO (and, before building, a probe pin's torque at each stake); the tree's weight by part, so its centre of mass is known (it sits 140cm below the hub, which is what lets a pick at the hub hang plumb); the robot's datasheet and its feet's grip; the helical-pile makers' torque-to-capacity tables; a slew drive's datasheet.
- Methods and tools
- A free body at every stage; 1.5 against overturning and sliding (BS 5975, ASCE 37); the wind's pressure ½ρV² on ASCE 7 force coefficients for the folded leaves and the stem; AC358's torque correlation, capacity = Kt × torque, with 2 on it; Euler for the tripod's legs; a gin-pole raise solved through its angle; a quadruped's grip on a rising line, μW·cosα / (cosα + μ·sinα); a hung load's pendulum stiffness; temporary helical pins; torque-logging drive heads and a clip-on inclinometer; a pull test on the first anchors.
- What shows it is right, other than us
- Published limits and plain physics, run by a test (scripts/test-solarform-props.mjs): every stage of every mechanism against the Unitree B2's published loads, the anchors' capacity from their own torque, the slew drive's datasheet, Euler and the wind's pressure. Checks that fail are shown failing. In the field: each screw's and anchor's torque log, a pull test on the first anchors, and an inclinometer on each tree before its kit comes off.
- The prompt, rewritten
- Build an anatomy lab of the temporary works that stand a SolarForm and hold it until its anchors are in, using what quadruped robots add: a self-erecting tripod that hangs the whole tree plumb from its hub and screws it down through a pinned stool; and foundation first — a pinned template through which the screw and anchors go in light — then either a gin pole and winch with robots on the guys, or a solar tracker's slew drive on a hinged flange; beside Fig 2's tilt-up jig. Model each stage as a free body from the room's numbers and published sources (the B2's loads, AC358, ASCE 7, the slew drive's datasheet, Waimānalo's wind and SSURGO soils), every quantity graded in the ledger: what each robot carries, lifts and holds, where every torque goes, the worst temporary state in a stop-work wind, its factor of safety, and what is left in the ground. Draw each as an interactive isometric figure at one scale, its readout and caption from that model, stage by stage. Add a test that checks every stage against those limits, shows what fails as failing, and proves nothing temporary is left. Push to main.