Two Maxes onto the one on the pad, three high, located by four stacking cones at each unit's corners, by a large forklift; the drone watches the cones meet; the quadrupeds tension tie-downs at the stack's ends for the design wind.

Progress

time a collision a check short

0 s
Forklift0 s–7 s To the staged Max 17 s–12 s Creep the forks into its pockets12 s–15 s Take its weight off the dunnage15 s–19 s Back out19 s–27 s Carry it toward the stack, forks low, planned for the unit it carries27 s–35 s Square up to the stack35 s–42 s Raise it to 2.25 m, clear of the cones on the unit below42 s–50 s Creep it over the stack57 s–1:01 Let it down: the cones find their sockets, the couplers mate as its weight comes on1:01–1:06 Draw the forks out and back off1:06–1:14 Lower the forks1:14–1:25 To the staged Max 21:25–1:30 Creep the forks into its pockets1:30–1:33 Take its weight off the dunnage1:33–1:38 Back out1:38–1:51 Carry it toward the stack, forks low, planned for the unit it carries1:51–1:59 Square up to the stack1:59–2:14 Raise it to 4.15 m, clear of the cones on the unit below2:14–2:22 Creep it over the stack2:22–2:26 Let it down: the cones find their sockets, the couplers mate as its weight comes on2:26–2:32 Draw the forks out and back off2:32–2:47 Lower the forks2:47–2:57 Park clearHow the unit rides to the stack
Quadruped 12:30–2:45 Give way to forklift2:45–2:53 Take strap 1's lower end to its ground anchor2:53–3:05 Hook it on the anchor and ratchet it to 4.5 kN3:05–3:09 Take strap 3's lower end to its ground anchor3:09–3:21 Hook it on the anchor and ratchet it to 4.5 kN3:21–3:25 Take strap 5's lower end to its ground anchor3:25–3:37 Hook it on the anchor and ratchet it to 4.5 kN3:37–3:40 Take strap 7's lower end to its ground anchor3:40–3:52 Hook it on the anchor and ratchet it to 4.5 kNHow the stack is held in the design wind
Quadruped 22:39–2:49 Take strap 2's lower end to its ground anchor2:49–3:01 Hook it on the anchor and ratchet it to 4.5 kN3:01–3:05 Take strap 4's lower end to its ground anchor3:05–3:17 Hook it on the anchor and ratchet it to 4.5 kN3:17–3:21 Take strap 6's lower end to its ground anchor3:21–3:33 Hook it on the anchor and ratchet it to 4.5 kN3:36–3:40 Take strap 8's lower end to its ground anchor3:40–3:52 Hook it on the anchor and ratchet it to 4.5 kN
Scanning drone44 s–47 s Lift off47 s–51 s Over the stack's corner51 s–57 s Check the four cones under their sockets: 5 mm off against their 12 mm lead2:16–2:22 Check the four cones under their sockets: 5 mm off against their 12 mm lead2:26–2:30 Fly strap 1's hook up to a top corner casting2:30–2:36 Hook it in the casting2:36–2:39 Fly strap 2's hook up to a top corner casting2:39–2:45 Hook it in the casting2:45–2:49 Fly strap 3's hook up to a top corner casting2:49–2:55 Hook it in the casting2:55–2:58 Fly strap 4's hook up to a top corner casting2:58–3:04 Hook it in the casting3:04–3:08 Fly strap 5's hook up to a top corner casting3:08–3:14 Hook it in the casting3:14–3:17 Fly strap 6's hook up to a top corner casting3:17–3:23 Hook it in the casting3:23–3:27 Fly strap 7's hook up to a top corner casting3:27–3:33 Hook it in the casting3:33–3:36 Fly strap 8's hook up to a top corner casting3:36–3:42 Hook it in the casting

working moving scanning waiting a choice a collision · click a lane to go there

Forklift's load moment, of its ratingest.

0 %of 100

Lateral tip angle at this fork heightest.

31 °of 60 · 3.4° needed

Couplers mating as it seatsest.

0 Nof 4120

Each strap at the design windest.

4.5 kNof 7.4

What it found

  • The forklift carries each 420 kg unit at 13 % of its load chart, and raised to the third level its stability triangle tips at 26°, against the 3.4° ISO 22915-2 asks. A large machine for a light load: it places to 5 mm, inside the cones' 12 mm lead, and holds the unit rigid where a hung one swings.
  • Dry, as it is built, the stack holds itself to the stop-work wind (its weight restores 5.6 kN·m against 1.4). Full, in the 58 m/s design wind, the wind's 57 kN·m against its weight's 21 would overturn it: it needs 36 kN of tie-down at its ends with 1.5 on it. 8 straps take 4.5 kN each, against an anchor's 7.4 kN allowable and a strap's 10 kN: they hold.

Every check in the run

the full stack in the 58 m/s design wind: its weight's moment against the wind's, with 1.5, its 8 straps holding the rest4.5 of 7.4 kN a strap

the load's moment against the forklift's rated chart4.1 of 30.9 kN·m

its stability triangle with the load at 2.3 m: the lateral tip angle against ISO 22915-2's test3.4 of 29.4 °

the lift height against the mast's 4.5 m2.25 of 4.50 m

the forks' placing error against the cones' lead5 of 12 mm

mating 8 couplers, against the unit's weight1368 of 4120 N

its stability triangle with the load at 4.1 m: the lateral tip angle against ISO 22915-2's test3.4 of 26.4 °

each strap's share of the tie-down at the design wind, against its anchor's allowable4.5 of 7.4 kN

Max stack · Two anchors to a corner0 s of 3:520 collisions8 of 8 checks holdrobots busy 6:41