A lane's lines in the ground: the chain trencher cuts and pays the loop's pipes, the cable and the collector off its reels; a quadruped holds them in their lanes where they touch down; the carrier beds them in sand and blades the spoil back in lifts; the plates compact each before the next; the tape a lift short of grade.
Progress
time a collision a check short
working moving scanning waiting a choice a collision · click a lane to go there
Trench cutder.
0.0 mof 10.0
Lines' width on the floorest.
40.0 cmof 40.0
Backfill to gradeder.
0 cmof 53
Compaction, s a metreder.
40 s/mof 60
What it found
- The chain cuts 40 cm for the lines' 38: four lines side by side with 15 mm between, 0.77 m deep so their tops lie 0.61 m down; the trencher makes 60 m an hour, 10 minutes for this 10 m.
- Off a reel 1.2 m up the HDPE won't bend tighter than 2.25 m (25× its diameter), so it touches the floor 3.0 m behind the boom. The quadruped walks the edge there, its arm holding the lines to 1 cm of their lanes: they lie in the 40 cm with 0 mm to spare.
- The sand comes 300 kg a trip, 5 trips for the 1.22 t this run takes; then the spoil goes back in 4 lifts of 15 cm, each compacted to 95 % before the next.
- 2 plates keep pace: 40 s a metre against the trencher's 60. Compaction, not digging, sets the lane's pace.
Every check in the run
the lines' width on the floor, held in their lanes, against the chain's cut0.400 of 0.400 m
the trench's depth, against what the chain cuts0.77 of 1.20 m
the trench's depth, against the depth a trench may stand open without shoring0.77 of 1.52 m
a 60 m lane's lines on the reels, against what the trencher carries270 of 600 kg
compaction's pace with 2 plates, against the trencher's40 of 60 s/m